Enter your search here

Permit Details for P16-006555

Permit Details

View Permit Card Certificate of Occupancy Unavailable Certificate of Completion Unavailable Schedule Inspection View / Cancel Inspections
ID: P16-006555
Status: ISSUED
Valuation: $656,671.11
Type: RESIDENTIAL BUILDING
New Single Family
RES : SNEW
Entered: Sep 09, 2016
Issued: Jun 19, 2017
Description: NEW SFR W/ IRR 50 HEADS RECLAIMED
Attachments: Attachments not available for this permit type.

Permit Location

* The locations mapped above are approximate.
** Some addresses were not mapped.

Online Fees and Payment Balance

Fees:$1,048.60
Trust-$1,008.60
Balance:$40.00
Pay Fees Now

Related Permits

Permit Number Balance Due Amount to Pay Add Selected
View in Cart In Cart
**Plan Review Fee
View Cart Add Selected to Cart
* Will include a 2.5% convenience fee.
**The plan review fee is the minimum amount you can pay. It is required for us to get started on your permit request and is already included in the total amount due.

Related Addresses

History

October 2017Inspection: 10 - 4 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Termite Report / Cert.

Inspector: ltso
Inspection: 10 - 2 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Drywall Screw

Inspector: JBUSALACCHI
September 2017Inspection: 9 - 28 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Insulation

Inspector: JBUSALACCHI
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Ext. Lath & Brick Tie

Inspector: JMCGOWAN
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: JMCGOWAN
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: JMCGOWAN
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ELEC: Temp Underground (TUG)

Inspector: JBUSALACCHI
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: JBUSALACCHI
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: NC - BLDG: Ext.Wall Dry-in/Flashing
missing slider on 2nd floor
Inspector: JBUSALACCHI
Inspection: 9 - 1 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: LBAR2
Inspection: 9 - 1 - 2017

Entered On: 6 - 14 - 2017
Inspection: NC - BLDG: Ext.Wall Dry-in/Flashing
2nd floor rear of building balcony slider door not installed, not ready
Inspector: LBAR2
August 2017Inspection: 8 - 31 - 2017

Entered On: 6 - 14 - 2017
Inspection: NOTE - BLDG: Ext.Wall Dry-in/Flashing
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 31 - 2017

Entered On: 6 - 14 - 2017
Inspection: NOTE - ROOF: Roof - Dry-in / Flashing
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 24 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: LBAR2
Inspection: 8 - 14 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: ESTEVENS
Inspection: 8 - 11 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: ESTEVENS
Inspection: 8 - 3 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: LBAR2
Inspection: 8 - 3 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: LBAR2
July 2017Inspection: 7 - 27 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: WHE99W
Inspection: 7 - 27 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: WHE99W
7 - 5 - 2017Notice
Formboard Approved
7 - 5 - 2017APPR: Development Review Approval
Formboard Approved
7 - 3 - 2017Comment
RCVD CHANGE OF SUB FORM TO REMOVE SR PLUMB & ADD FIRST QUALITY PLUMB. CHARGED $40 SCANNED TO SIRE
June 20176 - 19 - 2017Comment
Approved permit released for download.
6 - 19 - 2017Comment
NEED UTIL AFF/TUG, RCVD DUKE
6 - 19 - 2017Comment
NEE ALL STATE LICENSE UPDATED BEFORE ISSUANCE
6 - 19 - 2017Notice
FIRST APPLICATION EXTENSION APPROVED UNTIL 08/15/2017 (90) DAYS-SCANNED IN SIRE
6 - 19 - 2017Payment for: $1008.60
Payment Method: Trust
6 - 16 - 2017Comment
Plans electronically stamped
6 - 15 - 2017APC: Building Office Approval
P16-006555 B1. Just a reminder, handrail ends shall be returned to the wall or shall terminate in newel posts. FBCR 311.7.8.2 B2. Enclosed accessible space under stairs shall have walls, under-stair surface and any soffits protected on the enclosed side with ½ inch gypsum board. FBRC 2014 R302.7
6 - 14 - 2017Appr: 911 Communications Approval
6 - 14 - 2017Appr: Zoning Office Approval
P16-006555 SFR APPROVED SETBACKS-FRONT=20FT, REAR=20FT, SIDE=5FT, OSCEOLA COUNTY ZONING JMW 6/14/17
6 - 14 - 2017APC: Development Review Approval
Formboard Survey required prior to slab pour inspection LOT 37 REUNION WEST PH 3 WEST–FFE=149.7 FLOODZONE X DRIVEWAY AND SIDEWALK
6 - 14 - 2017Appr: Environmental Office Approval
6 - 14 - 2017Comment
Applicant uploaded documents. Routed for review.
6 - 14 - 2017Notice
Formboard Survey required prior to slab pour inspection LOT 37 REUNION WEST PH 3 WEST-FFE=149.7 FLOODZONE X DRIVEWAY AND SIDEWALK
May 20175 - 16 - 2017Comment
REC'D EXT REQUEST
February 20172 - 9 - 2017Comment
2-9-17 SENT LETTER PERMIT APPLICATION WILL EXPIRE 3-8-2017
January 20171 - 23 - 201701 : Zoning Office Approval
No Documents submitted to review
November 201611 - 9 - 2016APPR: Impact Fee Approval
September 20169 - 12 - 2016APPR: Health Dept Approval
9 - 9 - 2016Permit entered on September 9, 2016
9 - 9 - 2016Comment
RCVD VIA ONLINE, SENT TO SCANNING
9 - 9 - 2016Notice
NEED NOC ON JOBSITE
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BGII: General Inspection/Info
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Building - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Building - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Condemnation
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Ext.Wall Dry-in/Flashing
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Firestopping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Footings
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Framing
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Light Steel
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Notice of Commencement
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Slab on Grade
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Concrete
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Soil
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Struct Steel
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: DRYWALL: Drywall - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Underground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical Svc Upgrade
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Pre Power
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Temp Constr Power T-Pole
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas - Test / Rough-In
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas-Tanks/Buried Piping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH: Drainfield Construction
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH: Well Approved
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH:Mound Construction Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Duct / Exhaust / Hood
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Fire / Smoke Damper
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Underground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Electrical Service
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Mechanical
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Sewer / Water
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH Set / Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH Skirting Policy
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: D.W.V.
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Tubset
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Water Service
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM:Backflow/Cross Connection
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Alarm/Barrier
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Deck
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Piping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Steel and Ground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ROOF: Roofing - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: MH-Temp by BOA Removal
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Front Yard
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Rear Yard
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Side Yard
September 20169 - 9 - 2016Permit entered on September 9, 2016
July 20177 - 5 - 2017Notice
Formboard Approved
7 - 3 - 2017Comment
RCVD CHANGE OF SUB FORM TO REMOVE SR PLUMB & ADD FIRST QUALITY PLUMB. CHARGED $40 SCANNED TO SIRE
June 20176 - 19 - 2017Comment
Approved permit released for download.
6 - 19 - 2017Comment
NEED UTIL AFF/TUG, RCVD DUKE
6 - 19 - 2017Comment
NEE ALL STATE LICENSE UPDATED BEFORE ISSUANCE
6 - 19 - 2017Notice
FIRST APPLICATION EXTENSION APPROVED UNTIL 08/15/2017 (90) DAYS-SCANNED IN SIRE
6 - 16 - 2017Comment
Plans electronically stamped
6 - 14 - 2017Comment
Applicant uploaded documents. Routed for review.
6 - 14 - 2017Notice
Formboard Survey required prior to slab pour inspection LOT 37 REUNION WEST PH 3 WEST-FFE=149.7 FLOODZONE X DRIVEWAY AND SIDEWALK
May 20175 - 16 - 2017Comment
REC'D EXT REQUEST
February 20172 - 9 - 2017Comment
2-9-17 SENT LETTER PERMIT APPLICATION WILL EXPIRE 3-8-2017
September 20169 - 9 - 2016Comment
RCVD VIA ONLINE, SENT TO SCANNING
9 - 9 - 2016Notice
NEED NOC ON JOBSITE
July 2017Inspection: 7 - 27 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: WHE99W
Inspection: 7 - 27 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: WHE99W
August 2017Inspection: 8 - 3 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: LBAR2
Inspection: 8 - 3 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: LBAR2
Inspection: 8 - 11 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: ESTEVENS
Inspection: 8 - 14 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: ESTEVENS
Inspection: 8 - 24 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: LBAR2
Inspection: 8 - 31 - 2017

Entered On: 6 - 14 - 2017
Inspection: NOTE - BLDG: Ext.Wall Dry-in/Flashing
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 31 - 2017

Entered On: 6 - 14 - 2017
Inspection: NOTE - ROOF: Roof - Dry-in / Flashing
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
September 2017Inspection: 9 - 1 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: LBAR2
Inspection: 9 - 1 - 2017

Entered On: 6 - 14 - 2017
Inspection: NC - BLDG: Ext.Wall Dry-in/Flashing
2nd floor rear of building balcony slider door not installed, not ready
Inspector: LBAR2
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ELEC: Temp Underground (TUG)

Inspector: JBUSALACCHI
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: JBUSALACCHI
Inspection: 9 - 5 - 2017

Entered On: 6 - 14 - 2017
Inspection: NC - BLDG: Ext.Wall Dry-in/Flashing
missing slider on 2nd floor
Inspector: JBUSALACCHI
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Ext. Lath & Brick Tie

Inspector: JMCGOWAN
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: JMCGOWAN
Inspection: 9 - 25 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: JMCGOWAN
Inspection: 9 - 28 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Insulation

Inspector: JBUSALACCHI
October 2017Inspection: 10 - 2 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Drywall Screw

Inspector: JBUSALACCHI
Inspection: 10 - 4 - 2017

Entered On: 6 - 14 - 2017
Inspection: APPR - BLDG: Termite Report / Cert.

Inspector: ltso
September 2016Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BGII: General Inspection/Info
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Building - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Building - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Condemnation
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Ext.Wall Dry-in/Flashing
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Firestopping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Footings
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Framing
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Light Steel
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Notice of Commencement
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Slab on Grade
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Concrete
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Soil
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: BLDG: Spec Rpt Struct Steel
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: DRYWALL: Drywall - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical - Underground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Electrical Svc Upgrade
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Pre Power
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ELEC: Temp Constr Power T-Pole
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas - Test / Rough-In
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: GAS: Gas-Tanks/Buried Piping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH: Drainfield Construction
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH: Well Approved
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: HLTH:Mound Construction Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Duct / Exhaust / Hood
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Fire / Smoke Damper
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MECH: Mechanical - Underground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Electrical Service
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Mechanical
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH - Sewer / Water
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH Set / Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: MH: MH Skirting Policy
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: D.W.V.
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Other
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Plumbing - Rough-in
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Tubset
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM: Water Service
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: PLUM:Backflow/Cross Connection
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Alarm/Barrier
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Deck
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Piping
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: POOL: Pool - Steel and Ground
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ROOF: Roofing - Final
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: MH-Temp by BOA Removal
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Front Yard
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Rear Yard
Inspection: 9 - 9 - 2016

Entered On: 6 - 14 - 2017
Pending Inspection: ZONE: Setback-Side Yard
June 20176 - 19 - 2017Payment for: $1008.60
Payment Method: Trust
July 20177 - 5 - 2017APPR: Development Review Approval
Formboard Approved
June 20176 - 15 - 2017APC: Building Office Approval
P16-006555 B1. Just a reminder, handrail ends shall be returned to the wall or shall terminate in newel posts. FBCR 311.7.8.2 B2. Enclosed accessible space under stairs shall have walls, under-stair surface and any soffits protected on the enclosed side with ½ inch gypsum board. FBRC 2014 R302.7
6 - 14 - 2017Appr: 911 Communications Approval
6 - 14 - 2017Appr: Zoning Office Approval
P16-006555 SFR APPROVED SETBACKS-FRONT=20FT, REAR=20FT, SIDE=5FT, OSCEOLA COUNTY ZONING JMW 6/14/17
6 - 14 - 2017APC: Development Review Approval
Formboard Survey required prior to slab pour inspection LOT 37 REUNION WEST PH 3 WEST–FFE=149.7 FLOODZONE X DRIVEWAY AND SIDEWALK
6 - 14 - 2017Appr: Environmental Office Approval
January 20171 - 23 - 201701 : Zoning Office Approval
No Documents submitted to review
November 201611 - 9 - 2016APPR: Impact Fee Approval
September 20169 - 12 - 2016APPR: Health Dept Approval