Enter your search here

Permit Details for P16-006831

Permit Details

View Permit Card View Certificate of Occupancy Certificate of Completion Unavailable Schedule Inspection View / Cancel Inspections
ID: P16-006831
Status: CO
Valuation: $305,922.54
Type: RESIDENTIAL BUILDING
New Single Family
RES : SNEW
Entered: Sep 20, 2016
Issued: Jun 19, 2017
Description: 7734 FAIRFAX DRIVE KISSIMMEE, 34747 22-25-27-4924-0001-00B5 NEW SFR W/ IRR 50 HEADS RECLAIMED
Attachments: Attachments not available for this permit type.

Permit Location

* The locations mapped above are approximate.
** Some addresses were not mapped.

Online Fees and Payment Balance

Fees:$1,056.60
Trust-$1,008.60
Trust-$48.00
Balance:$0.00

Related Permits

Permit Number Balance Due Amount to Pay Add Selected
View in Cart In Cart
**Plan Review Fee
View Cart Add Selected to Cart
* Will include a 2.5% convenience fee.
**The plan review fee is the minimum amount you can pay. It is required for us to get started on your permit request and is already included in the total amount due.

Related Addresses

History

November 2017Inspection: 11 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Termite Report / Cert.

Inspector: ltso
11 - 1 - 2017APPR: RCO Health Dept Approval
11 - 1 - 2017NOTE: RCO Building Dept Approval
STILL NEED DW & TERMITE CERT
11 - 1 - 2017APPR: RCO Building Dept Approval
11 - 1 - 2017APPR: RCO Impact Fee Approval
11 - 1 - 2017APPR: RCO TOHO Approval
October 2017Inspection: 10 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Building - Final

Inspector: JMCGOWAN
10 - 27 - 2017Payment for: $48.00
Payment Method: Trust
September 2017Inspection: 9 - 29 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Pre Power

Inspector: JMCGOWAN
Inspection: 9 - 29 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: JMCGOWAN
Inspection: 9 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - PLUM: Sewer
no water in stack, needs 10' of head
Inspector: JBUSALACCHI
Inspection: 9 - 7 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Drywall Screw

Inspector: LHILTON
Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Insulation

Inspector: JBUSALACCHI
Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: LBAR2
August 2017Inspection: 8 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: Framing & Rough-Ins
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: NPDES Compliance
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 30 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 8 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Framing & Rough-Ins
Fbc110.5 Not ready for inspection - roof not complete. Straps not nailed off - valley, first floor-detail on straps, corner-second floor, rat runs exceed distance. P2503.5.1 10ft of head of water required. Discussed w/super & framer
Inspector: PSR44M
Inspection: 8 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: NPDES Compliance
1035 NOC
Inspector: PSR44M
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - BLDG: Framing & Rough-Ins
per John
Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - BLDG: NPDES Compliance
per John
Inspector: LBAR2
Inspection: 8 - 23 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext. Lath & Brick Tie

Inspector: LBAR2
Inspection: 8 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: LBAR2
Inspection: 8 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: LBAR2
Inspection: 8 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: LBAR2
Inspection: 8 - 10 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: PSR44M
Inspection: 8 - 8 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: JBUS
Inspection: 8 - 8 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - ROOF:Roof Sheathing

Inspector: JBUS
Inspection: 8 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Temp Underground (TUG)
emailed duke 8-1-17
Inspector: LBAR2
July 2017Inspection: 7 - 27 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: WHE99W
Inspection: 7 - 25 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: Lintel / Beam / Down Cel
due to workload rescheduled inspection
Inspector: LBAR2
Inspection: 7 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Lintel / Beam / Down Cel
Fbc110.5 Not ready for inspection - Not complete
Inspector: PSR44M
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: LBAR2
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: LBAR2
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Electrical - Underground

Inspector: LBAR2
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Concrete Encased Electro
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Monolithic Footing/Slab
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - ELEC: Electrical - Underground
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 14 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: provider
7 - 13 - 2017Notice
Formboard Approved
7 - 13 - 2017APPR: Development Review Approval
Formboard Approved
June 20176 - 19 - 2017Comment
Approved permit released for download.
6 - 19 - 2017Comment
NEED UTIL AFF/TUG, RCVD DUKE
6 - 19 - 2017Comment
SERVICEMASTER NEEDS UPDATED STATE LIC
6 - 19 - 2017Notice
FIRST APPLICATION EXTENSION APPROVED UNTIL 08/29/2017. CHARGED 40.00. SCANNED.
6 - 19 - 2017Payment for: $1008.60
Payment Method: Trust
6 - 16 - 2017Comment
Plans electronically stamped
6 - 15 - 2017Appr: Building Office Approval
P16-006831 B1. Just a reminder, handrail ends shall be returned to the wall or shall terminate in newel posts. FBCR 311.7.8.2
6 - 14 - 2017Appr: 911 Communications Approval
6 - 14 - 2017APC: Development Review Approval
DEV REV APPR - Formboard Survey required prior to slab pour inspection LOT 6 REUNION WEST PH 3 WEST–FFE=134.5 FLOODZONE X DRIVEWAY AND SIDEWALK
6 - 14 - 2017Appr: Zoning Office Approval
P16-006831 SFR APPROVED SETBACKS-FRONT=20FT, REAR=20FT, SIDE=5FT, OSCEOLA COUNTY ZONING JMW 6/14/17
6 - 14 - 2017Appr: Environmental Office Approval
6 - 14 - 2017Comment
Applicant uploaded documents. Routed for review.
January 20171 - 23 - 201701 : Zoning Office Approval
No Documents submitted to review
November 201611 - 3 - 2016APPR: Impact Fee Approval
September 20169 - 20 - 2016Permit entered on September 20, 2016
9 - 20 - 2016Comment
Application uploaded in Project Dox, (on line application from permitting office) WEB PERMIT - Waiting for uploads
9 - 20 - 2016APPR: Health Dept Approval
9 - 19 - 2016Comment
RCVD VIA ONLINE, SENT TO SCANNING
9 - 19 - 2016Notice
NEED NOC ON JOBSITE
September 20169 - 20 - 2016Permit entered on September 20, 2016
July 20177 - 13 - 2017Notice
Formboard Approved
June 20176 - 19 - 2017Comment
Approved permit released for download.
6 - 19 - 2017Comment
NEED UTIL AFF/TUG, RCVD DUKE
6 - 19 - 2017Comment
SERVICEMASTER NEEDS UPDATED STATE LIC
6 - 19 - 2017Notice
FIRST APPLICATION EXTENSION APPROVED UNTIL 08/29/2017. CHARGED 40.00. SCANNED.
6 - 16 - 2017Comment
Plans electronically stamped
6 - 14 - 2017Comment
Applicant uploaded documents. Routed for review.
September 20169 - 20 - 2016Comment
Application uploaded in Project Dox, (on line application from permitting office) WEB PERMIT - Waiting for uploads
9 - 19 - 2016Comment
RCVD VIA ONLINE, SENT TO SCANNING
9 - 19 - 2016Notice
NEED NOC ON JOBSITE
July 2017Inspection: 7 - 14 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: provider
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Concrete Encased Electro
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Monolithic Footing/Slab
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - ELEC: Electrical - Underground
not per plan electric conduit to kitchen island not installed.
Inspector: LBAR2
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: LBAR2
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: LBAR2
Inspection: 7 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Electrical - Underground

Inspector: LBAR2
Inspection: 7 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Lintel / Beam / Down Cel
Fbc110.5 Not ready for inspection - Not complete
Inspector: PSR44M
Inspection: 7 - 25 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: Lintel / Beam / Down Cel
due to workload rescheduled inspection
Inspector: LBAR2
Inspection: 7 - 27 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: WHE99W
August 2017Inspection: 8 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Temp Underground (TUG)
emailed duke 8-1-17
Inspector: LBAR2
Inspection: 8 - 8 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: JBUS
Inspection: 8 - 8 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - ROOF:Roof Sheathing

Inspector: JBUS
Inspection: 8 - 10 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: PSR44M
Inspection: 8 - 17 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: LBAR2
Inspection: 8 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: LBAR2
Inspection: 8 - 18 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: LBAR2
Inspection: 8 - 23 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Ext. Lath & Brick Tie

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - BLDG: Framing & Rough-Ins
per John
Inspector: LBAR2
Inspection: 8 - 24 - 2017

Entered On: 11 - 1 - 2017
Inspection: CA - BLDG: NPDES Compliance
per John
Inspector: LBAR2
Inspection: 8 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: Framing & Rough-Ins
Fbc110.5 Not ready for inspection - roof not complete. Straps not nailed off - valley, first floor-detail on straps, corner-second floor, rat runs exceed distance. P2503.5.1 10ft of head of water required. Discussed w/super & framer
Inspector: PSR44M
Inspection: 8 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - BLDG: NPDES Compliance
1035 NOC
Inspector: PSR44M
Inspection: 8 - 30 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 8 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: Framing & Rough-Ins
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
Inspection: 8 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: NOTE - BLDG: NPDES Compliance
Due to heavy work load I rescheduled this inspection for 9/01/17
Inspector: WHE99W
September 2017Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Framing & Rough-Ins

Inspector: LBAR2
Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Insulation

Inspector: JBUSALACCHI
Inspection: 9 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: NPDES Compliance

Inspector: LBAR2
Inspection: 9 - 7 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Drywall Screw

Inspector: LHILTON
Inspection: 9 - 28 - 2017

Entered On: 11 - 1 - 2017
Inspection: NC - PLUM: Sewer
no water in stack, needs 10' of head
Inspector: JBUSALACCHI
Inspection: 9 - 29 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - ELEC: Pre Power

Inspector: JMCGOWAN
Inspection: 9 - 29 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: JMCGOWAN
October 2017Inspection: 10 - 31 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Building - Final

Inspector: JMCGOWAN
November 2017Inspection: 11 - 1 - 2017

Entered On: 11 - 1 - 2017
Inspection: APPR - BLDG: Termite Report / Cert.

Inspector: ltso
October 201710 - 27 - 2017Payment for: $48.00
Payment Method: Trust
June 20176 - 19 - 2017Payment for: $1008.60
Payment Method: Trust
November 201711 - 1 - 2017APPR: RCO Health Dept Approval
11 - 1 - 2017NOTE: RCO Building Dept Approval
STILL NEED DW & TERMITE CERT
11 - 1 - 2017APPR: RCO Building Dept Approval
11 - 1 - 2017APPR: RCO Impact Fee Approval
11 - 1 - 2017APPR: RCO TOHO Approval
July 20177 - 13 - 2017APPR: Development Review Approval
Formboard Approved
June 20176 - 15 - 2017Appr: Building Office Approval
P16-006831 B1. Just a reminder, handrail ends shall be returned to the wall or shall terminate in newel posts. FBCR 311.7.8.2
6 - 14 - 2017Appr: 911 Communications Approval
6 - 14 - 2017APC: Development Review Approval
DEV REV APPR - Formboard Survey required prior to slab pour inspection LOT 6 REUNION WEST PH 3 WEST–FFE=134.5 FLOODZONE X DRIVEWAY AND SIDEWALK
6 - 14 - 2017Appr: Zoning Office Approval
P16-006831 SFR APPROVED SETBACKS-FRONT=20FT, REAR=20FT, SIDE=5FT, OSCEOLA COUNTY ZONING JMW 6/14/17
6 - 14 - 2017Appr: Environmental Office Approval
January 20171 - 23 - 201701 : Zoning Office Approval
No Documents submitted to review
November 201611 - 3 - 2016APPR: Impact Fee Approval
September 20169 - 20 - 2016APPR: Health Dept Approval