Enter your search here

Permit Details for P17-004432

Permit Details

View Permit Card Certificate of Occupancy Unavailable Certificate of Completion Unavailable Schedule Inspection View / Cancel Inspections
ID: P17-004432
Status: ISSUED
Valuation: $230,348.79
Type: RESIDENTIAL BUILDING
New Single Family
RES : SNEW
Entered: Jun 08, 2017
Issued: Jun 19, 2017
Description: NEW SINGLE FAMILY RESIDENCE
Attachments: Attachments not available for this permit type.

Permit Location

* The locations mapped above are approximate.
** Some addresses were not mapped.

Online Fees and Payment Balance

Fees:$808.60
Credit Crd-$808.60
Balance:$0.00

Related Permits

Permit Number Balance Due Amount to Pay Add Selected
View in Cart In Cart
**Plan Review Fee
View Cart Add Selected to Cart
* Will include a 2.5% convenience fee.
**The plan review fee is the minimum amount you can pay. It is required for us to get started on your permit request and is already included in the total amount due.

Related Addresses

History

August 2017Inspection: 8 - 3 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: RPIF
Inspection: 8 - 3 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: RPIF
July 2017Inspection: 7 - 26 - 2017

Entered On: 6 - 12 - 2017
Inspection: CR - ELEC: Temp Underground (TUG)
not ready no underground
Inspector: LMW47B
Inspection: 7 - 20 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: DMID
Inspection: 7 - 20 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: DMID
Inspection: 7 - 7 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: LMW47B
June 2017Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: MJW67N
Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: MJW67N
Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ELEC: Electrical - Underground

Inspector: MJW67N
Inspection: 6 - 27 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: MJW67N
Inspection: 6 - 27 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: MJW67N
6 - 27 - 2017Notice
Formboard Approved
6 - 27 - 2017APPR: Development Review Approval
Formboard Approved
6 - 19 - 2017Comment
NEEDS TUG AND UTILITY AFF - RECV OUC
6 - 19 - 2017Comment
Approved permit released for download.
6 - 14 - 2017APPR: Impact Fee Approval
6 - 13 - 2017Comment
Plans electronically stamped
6 - 13 - 2017Payment for: $808.60
Payment Method: Credit Crd
6 - 13 - 2017Appr: Building Office Approval
6 - 12 - 2017Appr: Zoning Office Approval
ZONING APPR - P17-004432 SFR SETBACKS FRONT GARAGE= 20' FRONT= 10' REAR= 15' SIDES= 5 STREET SIDE= 10' ZONING APPROVED (CZEP) 06/12/2017
6 - 12 - 2017APC: Development Review Approval
DEV REVIEW - FORMBOARD SURVEY REQUIRED PRIOR TO SLAB POUR INSPECTION. LOTS 28 NARCOOSSEE DEL SOL FFE 80.00 FLOOD ZONE “X” DRIVEWAY & SIDEWALK
6 - 12 - 2017Appr: Environmental Office Approval
6 - 12 - 2017Appr: 911 Communications Approval
6 - 12 - 2017Comment
Applicant uploaded in project dox. Routed for review.
6 - 12 - 2017Notice
FORMBOARD SURVEY REQUIRED PRIOR TO SLAB POUR INSPECTION. LOTS 28 NARCOOSSEE DEL SOL FFE 80.00 FLOOD ZONE "X" DRIVEWAY & SIDEWALK
6 - 8 - 2017Permit entered on June 8, 2017
6 - 8 - 2017Comment
WEB Documents(Permit app) uploaded in Project Dox 06.08.17
6 - 8 - 2017Comment
WEB PERMIT
6 - 8 - 2017Notice
NEEDS NOC ON JOBSITE
6 - 8 - 2017APPR: Health Dept Approval
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BGII: General Inspection/Info
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Building - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Building - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Condemnation
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Drywall Screw
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Ext. Lath & Brick Tie
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Firestopping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Footings
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Framing
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Framing & Rough-Ins
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Insulation
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Light Steel
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Notice of Commencement
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: NPDES Compliance
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Slab on Grade
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Concrete
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Soil
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Struct Steel
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Termite Report / Cert.
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: DRYWALL: Drywall - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical Svc Upgrade
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Pre Power
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Temp Constr Power T-Pole
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Temp Underground (TUG)
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas - Test / Rough-In
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas-Tanks/Buried Piping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH: Drainfield Construction
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH: Well Approved
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH:Mound Construction Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Duct / Exhaust / Hood
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Fire / Smoke Damper
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Underground
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Electrical Service
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Mechanical
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Sewer / Water
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH Set / Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH Skirting Policy
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: D.W.V.
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Tubset
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Water Service
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM:Backflow/Cross Connection
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Alarm/Barrier
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Deck
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Piping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Steel and Ground
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ROOF: Roofing - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: MH-Temp by BOA Removal
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Front Yard
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Rear Yard
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Side Yard
June 20176 - 8 - 2017Permit entered on June 8, 2017
6 - 27 - 2017Notice
Formboard Approved
6 - 19 - 2017Comment
NEEDS TUG AND UTILITY AFF - RECV OUC
6 - 19 - 2017Comment
Approved permit released for download.
6 - 13 - 2017Comment
Plans electronically stamped
6 - 12 - 2017Comment
Applicant uploaded in project dox. Routed for review.
6 - 12 - 2017Notice
FORMBOARD SURVEY REQUIRED PRIOR TO SLAB POUR INSPECTION. LOTS 28 NARCOOSSEE DEL SOL FFE 80.00 FLOOD ZONE "X" DRIVEWAY & SIDEWALK
6 - 8 - 2017Comment
WEB Documents(Permit app) uploaded in Project Dox 06.08.17
6 - 8 - 2017Comment
WEB PERMIT
6 - 8 - 2017Notice
NEEDS NOC ON JOBSITE
June 2017Inspection: 6 - 27 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - PLUM: Plumbing - Underground

Inspector: MJW67N
Inspection: 6 - 27 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - PLUM: Sewer

Inspector: MJW67N
Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Concrete Encased Electro

Inspector: MJW67N
Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Monolithic Footing/Slab

Inspector: MJW67N
Inspection: 6 - 28 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ELEC: Electrical - Underground

Inspector: MJW67N
July 2017Inspection: 7 - 7 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Lintel / Beam / Down Cel

Inspector: LMW47B
Inspection: 7 - 20 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Ext. Sheathing/Strapping

Inspector: DMID
Inspection: 7 - 20 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ROOF:Roof Sheathing

Inspector: DMID
Inspection: 7 - 26 - 2017

Entered On: 6 - 12 - 2017
Inspection: CR - ELEC: Temp Underground (TUG)
not ready no underground
Inspector: LMW47B
August 2017Inspection: 8 - 3 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - BLDG: Ext.Wall Dry-in/Flashing

Inspector: RPIF
Inspection: 8 - 3 - 2017

Entered On: 6 - 12 - 2017
Inspection: APPR - ROOF: Roof - Dry-in / Flashing

Inspector: RPIF
June 2017Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BGII: General Inspection/Info
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Building - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Building - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Condemnation
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Drywall Screw
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Ext. Lath & Brick Tie
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Firestopping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Footings
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Framing
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Framing & Rough-Ins
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Insulation
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Light Steel
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Notice of Commencement
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: NPDES Compliance
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Slab on Grade
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Concrete
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Soil
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Spec Rpt Struct Steel
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: BLDG: Termite Report / Cert.
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: DRYWALL: Drywall - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Electrical Svc Upgrade
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Pre Power
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Temp Constr Power T-Pole
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ELEC: Temp Underground (TUG)
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas - Test / Rough-In
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: GAS: Gas-Tanks/Buried Piping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH: Drainfield Construction
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH: Well Approved
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: HLTH:Mound Construction Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Duct / Exhaust / Hood
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Fire / Smoke Damper
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MECH: Mechanical - Underground
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Electrical Service
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Mechanical
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH - Sewer / Water
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH Set / Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: MH: MH Skirting Policy
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: D.W.V.
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Other
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Plumbing - Rough-in
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Tubset
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM: Water Service
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: PLUM:Backflow/Cross Connection
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Alarm/Barrier
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Deck
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Piping
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: POOL: Pool - Steel and Ground
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ROOF: Roofing - Final
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: MH-Temp by BOA Removal
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Front Yard
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Rear Yard
Inspection: 6 - 8 - 2017

Entered On: 6 - 12 - 2017
Pending Inspection: ZONE: Setback-Side Yard
June 20176 - 13 - 2017Payment for: $808.60
Payment Method: Credit Crd
June 20176 - 27 - 2017APPR: Development Review Approval
Formboard Approved
6 - 14 - 2017APPR: Impact Fee Approval
6 - 13 - 2017Appr: Building Office Approval
6 - 12 - 2017Appr: Zoning Office Approval
ZONING APPR - P17-004432 SFR SETBACKS FRONT GARAGE= 20' FRONT= 10' REAR= 15' SIDES= 5 STREET SIDE= 10' ZONING APPROVED (CZEP) 06/12/2017
6 - 12 - 2017APC: Development Review Approval
DEV REVIEW - FORMBOARD SURVEY REQUIRED PRIOR TO SLAB POUR INSPECTION. LOTS 28 NARCOOSSEE DEL SOL FFE 80.00 FLOOD ZONE “X” DRIVEWAY & SIDEWALK
6 - 12 - 2017Appr: Environmental Office Approval
6 - 12 - 2017Appr: 911 Communications Approval
6 - 8 - 2017APPR: Health Dept Approval